Seymour will revert back to its original timetable while Shepparton will move into a temporary timetable

V/Line has completed its $9 million program to replace more than 31,000 sleepers on the line between Seymour and Melbourne.
 
The temporary timetable in place while the works bedded down is no longer required and trains will resume running the normal timetable on the Seymour line from Sunday 29 September.
 
Works will now move to the Shepparton line, where more than 37,000 sleepers will be replaced between Seymour and Shepparton.
 
To continue to provide a reliable journey for customers, a revised temporary timetable will be in place for Shepparton customers from Wednesday 2 October.
 
Trains to Melbourne will depart from stations between Shepparton and Nagambie two minutes earlier than the normal timetable. Trains from Melbourne will arrive into Shepparton two minutes later than normal.
 
Trains will arrive and depart at normal times between Seymour and Melbourne.
 
Customers should arrive in time for their service as it is displayed timetable.
 
Customers can request a printed copy at staffed V/Line stations, premium metropolitan stations, V/Line ticket agents, PTV hubs or by calling 1800 800 007.