Fully tunneling is planned to be completed by the end of the year.

Almost half of the tunnels between the Mamyri and Bachurinskaya stations of the Troitskaya metro line have been passed, said the Deputy Mayor of Moscow for Urban Development and Construction Andrey Bochkarev

“The section with two single-track tunnels between the Mamyri and Bachurinskaya station complexes of the future Troitskaya line has been completed by 47 percent. The tunneling is planned to be completed by the end of the year, ”he said.

The construction of a tunnel has begun on the Mamyri – Bachurinskaya section of the Troitskaya metro line

The shield “Eugene” in the right tunnel has overcome 1254 meters, and the tunnel boring complex “Daria” in the left tunnel – 1114 meters. The station is separated by more than 2500 meters.

“At the stations of the first 13-kilometer construction stage of the Troitskaya line from Novatorskaya to Bachurinskaya, the general construction readiness of which is estimated at 41 percent, active work continues,” added Andrei Bochkarev.

At the stations “Ulitsa Generala Tyuleneva” and “Mamyri”, more than a quarter ready, monolithic work continues, including the construction of lobbies. And at Novatorskaya and Tyutchevskaya, they have already begun the architectural decoration of the office premises – the readiness of these stations is more than 40 percent.

“Of the five station complexes of this section, the highest degree of readiness is the Peoples’ Friendship University, where backfilling of the foundation pit and installation of engineering systems are already being carried out. Its readiness is about 57 percent, “said Yuri Kravtsov, General Director of Mosinzhproekt, a management company that builds new lines and metro stations.

The Troitskaya line will run from the Moscow Central Ring to the Troitsk urban district, its length will be almost 40 kilometers. It is expected that the branch will be used by about 100 thousand people daily. More than a million people live near the stations, and several hundred thousand more citizens work or study.