MIL OSI Translation. Region: Russian Federation –

September 7, 2021, 07:04

Share this

Photo by E. Samarin. Press Service of the Mayor and the Moscow Government

Major repairs have already been completed by 45 percent.

Two new premises were selected for the children’s dental clinic No. 52. Some of the employees will move to building 18a, building 2 on Koptevskaya street, and the other to the building at 4 Ivan Susanin street, building 1. There is a major overhaul at the moment. It has already been completed by 45 percent. The work is carried out on an area of ​​over 600 square meters.

Now the clinic is located on the first floor of a five-story residential building in the 3rd Mikhalkovsky lane. This building was included in the renovation program, so the premises must be vacated.

Local residents are accustomed to the fact that children’s dentistry is nearby, and when choosing a new premises, the specialists took this fact into account. As a result, the clinic will be located in the same area, and residents will be able to take their children to the doctors they are used to.

All dismantling works in the room have already been completed, the ceiling joints have been repaired, new internal partitions have been erected, a new floor screed has been made, and the door and window openings have been reinforced.

“Now work is underway on the rough finishing of the interior and the repair of the entrance lobbies. We have almost finished the insulation and the installation of a new roof. Soon they will start assembling new and modern engineering systems, installing doors and windows. The facade will also be put in order – they will insulate, plaster and re-paint in accordance with the passport of the coloristic solution, ”said the deputy head

Department of overhaul of the city of Moscow Denis Lebedev.

On the ground floor, there will be a storage area for strollers, a lobby with a reception and a wardrobe. There will be offices of an orthodontist, a radiologist, two offices of therapeutic dentistry, offices of a surgeon and a dental technician. In addition, a mother and child room will appear, as well as administrative and utility rooms.

“The existing basement under the building will be adapted for warehouses for various purposes, a sterilization room, and for the employees there will be made women’s and men’s wardrobe, showers, as well as a room for eating,” added Denis Lebedev.

It is planned to complete the main construction and installation work in the fourth quarter of 2021.

By the end of 2023, more than 70 healthcare facilities will be built in the capital at the expense of the city and investors.

EDITOR’S NOTE: This article is a translation. Apologies should the grammar and or sentence structure not be perfect.