Photo by E. Samarin. Mos.ru

We repaired sections of the Garden Ring, 1st Tverskaya-Yamskaya Street, Leningradsky Prospekt, Entuziastov Highway and other key highways.

Work on road repairs in preparation for winter has been completed by 92 percent and will be fully completed by October 1, said the Deputy Mayor of Moscow for Housing and Utilities and Improvement Peter Biryukov… This year, it is planned to repair about 2.8 thousand road facilities with a total area of ​​over 23 million square meters.

“Currently, the work is 92 percent completed, it will be completed on time, by October 1,” said Pyotr Biryukov. “One of the tasks is to remove the rut, which was formed due to heavy traffic and temperature changes, as it can cause an accident.”

Works on the repair of sections of the Garden Ring, 1st Tverskaya-Yamskaya Street, key outbound highways – Leningradsky Prospect, Entuziastov Highway, M3 “Ukraine” highway, Leningradskoye, Varshavskoye, Kashirskoye, Shchelkovskoye, Ostashkovskoye, Kievskoye and Novoryazanskoye highways have been completed.

Currently, work is being carried out at more than 150 objects, including sections of the Moscow Ring Road, the Luzhnetskaya overpass of the Third Transport Ring (from Andreevsky Bridge to Berezhkovsky Bridge), Krylatskie Holmy and Shirokaya Streets, Brateevsky Most.

The head of the municipal economy complex noted that after the completion of the asphalt concrete pavement, the center lines of the road marking will be applied, dividing the traffic flows in opposite directions, after 10 days – lane lines, pedestrian crossings, stop lines, arrows, duplicate road signs and markings of public transport stops.