For high-quality and uninterrupted provision of the heating period of 2021–2022, the branch of the Federal State Budgetary Institution “Central Housing and Communal Administration” of the Ministry of Defense of Russia (according to the 12th GU MO) completed the current repair of boiler equipment at the boiler house in the military town of Sergiev Posad district of the Moscow region, the village of Sharapovo.

The renovated boiler house provides hot water supply and heat to 24 buildings of the barracks and housing stock and three hostels. Specialists of the production site in Sergiev-Posad, Moscow Region, branch of the FGBU “TsZhKU” of the Ministry of Defense of Russia (12 GU MO) signed a contract for the implementation of routine repairs by a contractor.

The technical complex of the boiler house is in continuous operation throughout the year. To ensure the stable performance and reliability of the equipment, it is planned to carry out seasonal routine maintenance, during which parts and assemblies with a high degree of wear are determined, and a complete examination of the condition of the boiler equipment is carried out. The main task of the survey is to restore to its original state and improve the performance of the boiler plant.

In addition, work was carried out to replace the pipe part of the DE-6,5 / 14 GM steam boiler, and the installation of pipelines within the boiler, as well as the boiler feed line was carried out. Hydraulic tests of the installed pipe part have been carried out. In addition, the boiler lining was completed, which includes a complex and high-tech process, the installation of a system of refractory and heat-insulating fences for the boiler and the combustion chamber.

In the near future, the work on connecting the automation and control panels will be completed, after which the specialists will carry out commissioning. After receiving the permitting documentation, the boiler will be put into operation.

In order to ensure continuous operation during the heating period of the boiler houses located in the territory of the Moscow Region, the supply of liquid and solid fuels has been completed, the necessary regulatory reserves have been created.